Q146. Which three are true about Database Point-in-Time Recovery?

Q146. Which three are true about Database Point-in-Time Recovery? (Choose three.)

A. The database must have FLASHBACK DATABASE ON to perform Database Point-in-Time Recovery.
B. The database must be in MOUNT state when performing Database Point-in-Time Recovery.
C. Database Point-in-Time Recovery is performed by the Managed Recovery Process (MRP)
D. The Database must be in ARCHIVELOG mode.
E. The target point for the recovery must be specified as a stime or System Change Number (SCN).
F. The database must be open RESETLOGS after Database Point-in-Time Recovery.